Ruta critica

Ruta critica :

1-3-4-5-9-10-11-18-19

t=131 días

$500(131)= $65,500

$N= $ 113,200

Costo total = $ 178,700


Ruta tiempo optimo:

t= 61 días

A.1= 7 x 0.857 = 6

A.3 = 6 x 0.125= 0.75

A.4 = 7 x 0 = 0

A.5 = 13 x 0.461= 6

A.9 = 3 x 0.66 = 1.98

A.10 = 3 x 0.66= 1.98

A.11= 1 x 0= 0

A.18 = 1x 0 = 0

A.19 = 21 x 0= 0

$m Actividades = $ 16,710

61 ($500)= $ 30,500

$N= $ 113,200

Costo optimo= $ 160,410