Ruta critica
Ruta critica :
1-3-4-5-9-10-11-18-19
t=131 días
$500(131)= $65,500
$N= $ 113,200
Costo total = $ 178,700
Ruta tiempo optimo:
t= 61 días
A.1= 7 x 0.857 = 6
A.3 = 6 x 0.125= 0.75
A.4 = 7 x 0 = 0
A.5 = 13 x 0.461= 6
A.9 = 3 x 0.66 = 1.98
A.10 = 3 x 0.66= 1.98
A.11= 1 x 0= 0
A.18 = 1x 0 = 0
A.19 = 21 x 0= 0
$m Actividades = $ 16,710
61 ($500)= $ 30,500
$N= $ 113,200
Costo optimo= $ 160,410